    PV project at our plant in Zibo, China

    More ...
     
     

    PV project at our plant in Zibo, China

    After 75 days of construction and commissioning, the Photovoltaic project at the Zibo Refratechnik Refractories plant came into use on June 15, 2026.
    The total installation area is 15,000 square meters with battery of 1,000 kWh and the annual power generation will be around 1.7 million kWh.
    The main part of power shall be self-consumed.
     
    Follow us!
    Privacy settings
    This website uses cookies and techniques of external service providers. Some of them are necessary, and others help us to improve this website and your experience of it. These techniques can collect personal data. Here, we want to give you the opportunity to decide yourself which services/providers may collect your data. You can change/revoke your selection at any time later on our data protection page in the form provided there.